Projects

Edita Factory

Description:

The restoration of the 500 m length loading dock of the main building in the “Edita” factory in “Al Sheikh Zaid” city.

The Challenge:

The existence of many cracks in the concrete slab and the solution was to break the whole slab and make a new on.

However we found a better solution which was to break all the separators and pour the high resistant grout material “Master Emaco 488” and mix it with the epoxy material “Master brace 1414”

This solution saved 1.5 million L.E. .